The build is the short part. Below is what the calendar actually looks like on a West County multi-feature project, phase by phase, and when to sign to hold a spring slot.
| Phase | Duration |
|---|---|
| Design, revisions, material selection | 2 - 6 weeks |
| Permitting and any engineered wall review | 2 - 6 weeks |
| Material lead time, in season | 4 - 10 weeks |
| Excavation, grading, drainage | 3 - 9 days on site |
| Wall construction and backfill | 4 - 12 days on site |
| Patio base, laying, cutting, jointing | 5 - 12 days on site |
| Features, lighting, punch list | 3 - 8 days on site |
How long does a West County backyard build take?
Straight answerA standalone paver patio typically takes one to two weeks on site. A multi-feature build with walls, steps and a fire feature usually runs three to six weeks of active work, inside a four to eight month calendar once design, permits and material lead times are counted.
Why is the calendar so much longer than the build?
Straight answerDesign and revisions take two to six weeks, permitting in West County municipalities two to six more, and stone or coping lead times run four to ten weeks in season. Actual digging is the short part of the project.
When should I sign to build next spring?
Straight answerLate summer or fall. Good West County crews fill the spring calendar by roughly December, and signing in March for a May start usually means either a rushed design or a different builder than the one you wanted.
Can hardscape be installed in a Missouri winter?
Straight answerBase and wall work can continue in cold weather as long as the ground is not frozen and the aggregate is dry, and winter work often gets better crew attention. Polymeric jointing sand and some adhesives are the parts that genuinely need warmer, dry conditions.
What does a realistic payment schedule look like?
Straight answerA design fee up front, a deposit at contract that covers material, one or two progress payments tied to completed phases, and a final payment at punch-list sign-off. Be cautious about anything asking for a majority of the project total before excavation begins.
How should a phased build be sequenced?
Straight answerDesign the whole yard first, then build from the far side inward so equipment never has to cross finished work. Drainage and any wall that supports another feature go in phase one, regardless of which feature you want most.